格式:pdf
大小:58KB
頁數(shù): 10頁
寶潔技術(shù)中心 一次成型地面施工措施 - 1 - 一、construction brief 施工概況 According to change order, concrete layer of water process room and civil defense in R&D should be polished at one time. 根據(jù)設(shè)計(jì)變更要求,研發(fā)樓水處理間及人防地面混凝土一次性 壓光,采用混凝土地面一次成型施工工藝。 二、difficulties 難點(diǎn) 1、starting time is December 20 which is the coldest time in winter. Insulation and concrete curing are the most difficulty points. 開始施工地面時(shí)間為 12 月 20 日,進(jìn)入冬期施